with lots of information about our emerging proposals to Redevelop
Shinfield Park near Shinfield (formerly known as Shire Hall).
Our ambition for the site is to provide a more meaningful contribution to the local economy and assist Wokingham Borough Council with meeting some of the identified need for additional industrial floorspace within the Borough.
The proposed redevelopment of Shinfield Park (formally known as Shire Hall) will provide new sensitively designed and highly sustainable industrial/employment facilities with the creation of workplaces that focus on the wellbeing of future tenants and employees.
We consulted with the community and held an online public webinar with a Q&A session on Wednesday 15th January 2025. We would like to thank everyone who has shown an interest in our proposal and shared their valuable comments, suggestions and opinions with us.
You can find information on the scheme we consulted on in the Emerging Proposal section and PDF copies of the consultation materials including a recording of the webinar are available in the Library section.
The information and material on this website relates to the pre-application consultation period which was held in January 2025 and will remain accessible until the planning application has been determined.
Background & Location
Who are Wrenbridge?
Wrenbridge is a leading UK property company founded in 1993 who have been successfully developing and investing in properties across the UK for over 25 years.
As a specialist in industrial redevelopment projects, Wrenbridge prides itself on the design and quality of its developments, which are valued by their tenants, partners and neighbours. Wrenbridge take adding positively to the built environment very seriously and work closely with its design team, landowners and stakeholders to bring forward projects that are both viable and sustainable, to create high quality next generation development.
Shinfield Park is an existing employment site, located within a major development location. The site is located to the north of Shinfield and to the south of Reading. It is bounded to the east by Whitley Wood Lane and is accessed off Lower Early Way/B3270 via Whitley Wood Lane. To the south is the M4 Motorway with Junction 11 about a mile away. To the west of the site is mature woodland. Residential properties sit beyond the site to the north and west. The Thames Valley Science Park and Shinfield Studios are also in close proximity to the site.
A Public Right of Way (‘PROW’) crosses the site to the north, connecting Greenwich Road to Railton Close.
Site location plan showing the area for the proposed redevelopment outlined in red.
The Site is approximately 5.5 hectares (13.64 acres) and currently comprises an existing geometric-shaped office building extending up to 4-storeys plus basement car parking. A detached 3-storey modular office building to the north of the main office building has recently been removed. The Site also contains internal access roads, surface level car parking, two residential properties to the north of the site, and there are a number of existing, established trees. The area to the south of the main office building comprises mature woodland and ponds.
The adopted Wokingham Borough Local Plan supports the redevelopment of buildings within employment use subject to there being no overall net loss of employment floorspace within the Borough. This encourages the use of existing employment sites to remain in active employment use.
The Council are currently in the process of producing a new Local Plan and the evidence base identifies an overall surplus of office floorspace (and advising that some of this should be released for other uses) and low provision but strong demand for additional industrial floorspace in the Borough.
Site History
The site has an extensive history dating back to the 1940s when it was used by the RAF for the Unit Headquarters of Training Command. By the 1970s, any buildings associated with the RAF had been removed, and in early 1976 works to erect a new administrative home for Berkshire County Council (known as Shire Hall) commenced, with the office complex subsequently completed and operational by 1982.
Following the abolition of the County Council during the 1998 local government reforms, the site was subsequently occupied by Foster Wheeler, which later merged into Wood Group PLC in 2017. Under the occupation of Wood Group PLC, the amount of office floorspace on the site was extended in the form of a temporary modular building, originally approved in 2006. However, in more recent years, the site has become surplus to Wood’s requirements, and they have subsequently moved to new premises at Green Park, Reading.
In August 2024, the site was acquired by Wrenbridge (FRELD Reading) LLP.
Click the arrows below to scroll through the images:
Aerial view of site looking west
Aerial view of site looking south
Existing site image showing site entrance off the B3270.
Existing site image showing office building from site entrance.
Key Development Priorities
Shinfield Park (formerly known as Shire Hall) is being proposed for redevelopment as the existing office building is no longer fit for purpose and is surplus to requirements in the Borough. Office employment-based businesses are choosing smaller office spaces located closer to town centres to respond to the recent changes in work habits post-Covid-19 pandemic (including more flexibility and working from home).
Our priority for Shinfield Park is focused on providing new sensitively designed and modern industrial/employment facilities to bring an underutilised employment site back into meaningful use as encouraged by the Council’s Local Plan policy.
1. Re-use of vacant site
Bring a vacant site back into meaningful use.
Provide new industrial/employment space aimed at accommodating a range of businesses.
Generate new employment opportunities within the local area during construction and when operational.
Create attractive new workplaces with an emphasis on health and the wellbeing of future employees.
2. Modern and sustainable facilities
Provide modern facilities using contemporary and sustainable construction methods.
Create sensitively designed and flexible new industrial/employment facilities that can adapt to future occupier requirements and changing markets.
Achieve market-leading sustainability credentials, including BREEAM ‘Excellent’ and an EPC ‘A’ rating.
3. Protection of existing landscape
Safeguard existing Ancient Woodland and Local Wildlife sites to the north and west.
Retain the existing Public Right of Way (PROW) running through the northern part of the site.
Provide new facilities set back from residential areas with enhanced planting and landscape buffers.
Deliver enhanced landscaping throughout the site and net gains in biodiversity.
Retain and protect existing ponds along the western part of the site.
The Emerging Proposals
We are still in the early design stage, but this illustrative masterplan shows how we think the new buildings, access routes, and landscaped areas could be delivered on the site.
Illustrative Masterplan (click to enlarge)
Five modern and sustainable industrial/employment buildings providing a total of six new units, with the tallest building having a maximum height of 12 metres (16.57m to ridge).
Existing site entrance retained.
Secure bicycle shelters provided throughout the site. Providing 104 cycle parking spaces and 11 motorbike spaces.
Existing Public Right of Way footpath retained.
Additional planting around site boundaries to provide a green buffer to residential areas and support the creation of new wildlife habitats.
226 car parking spaces including 14 reduced mobility spaces and 45 EV charging points (with infrastructure for further expansion).
New landscaping to promote biodiversity throughout the site.
Outdoor seating and amenity areas for employees and site visitors.
Woodland car park to the north of the site for Unit 5 and overflow parking.
Existing Nores Hills Wood Ancient Woodland protected.
Click the arrows below to scroll through the images:
Illustrative image showing Unit 1 south elevation.
Illustrative image showing Unit 1 west elevation.
Illustrative image showing Unit 4 south elevation.
Illustrative image showing Unit 4 west elevation.
Illustrative image showing Unit 5 west elevation.
Illustrative image showing Unit 5 south elevation.
Illustrative view of Unit 1 and Unit 5 from site entrance.
Illustrative view of Unit 1 and Unit 4 from site entrance.
Illustrative view of Unit 4
Landscape and Ecology
Our landscape and ecology strategy aims to create a high-quality environment for new employees and visitors.
Proposed landscape and ecology plan showing precedent images for key areas. (click to enlarge)
New landscaping to promote biodiversity and to provide an enhanced landscape buffer and screening to existing residential homes to the north.
Designated Local Wildlife Site respected and protected, and existing ponds retained to safeguard biodiversity.
Enhanced access and green infrastructure links to ponds.
New external employee and site visitor amenity/ break out space.
Creation of a woodland car park as part of the site wide green infrastructure.
Existing mature tree belt maintained where possible.
Outdoor seating areas provided within landscaped areas for employees and site visitors.
Protection of Nores Hill Wood Ancient Woodland with enhanced buffer planting between new facilities and the Ancient Woodland boundary.
Click the arrows below to scroll through the images:
Dedicated Pedestrian-Cycle Route
Native Mixed Species Hedge
Meadow planting to south facing frontage banks within site boundary
Rain gardens
Biodiverse Flower rich Planting to Amenity Spaces
Tree Buffer and Seasonal Planting to Entrance
Access Transport
Our access and transport strategy aims to ensure safe and convenient access for employees and visitors.
Access and Transport Plan (click to enlarge)
Access
Access to the site will be via the existing junction connected to Lower Early Way (B3270).
Provision of new internal roads will facilitate safe vehicular, pedestrian and cycle access across the site.
Yards will be secured with gates to control pedestrian and vehicular access to industrial units.
The nearest bus stops are located approximately 500m from the site on Shinfield Road. This bus stop serves the Leopard 3 route which provides services to Reading railway station and runs 3-4 buses per hour in each direction.
Cycle and Pedestrian
Pedestrian and cycle routes are proposed throughout the site for employees and site visitors.
104 secure cycle storage spaces to encourage alternative modes of transport and to reduce reliance on private car use.
Retention of the Public Right of Way (PROW) that runs from Railton Close connecting to Greenwich Road on the site’s northern and western boundaries.
More sympathetic landscaping around the boundaries of the PROW where it traverses the northern part of the Site .
Existing trees and bank retained.
Existing Public Right of Way Existing Public Right of Way
Car Provision
226 car parking spaces and 14 reduced mobility spaces, are proposed throughout the site.
Conversion of existing car park to create a new woodland overflow car park and parking for Unit 5, with a green buffer to residential homes on the northern edges of the site.
45 Electric vehicle charging points will be provided to encourage the use of electric vehicles, with the necessary infrastructure provided for further expansion in the future.
104 cycle parking spaces and 11 motorbike spaces.
Drainage and Flooding
Surface Water Drainage
A variety of SuDS features have been incorporated within the proposals to reduce flood risk and promote amenity and biodiversity.
A series of Rain Gardens along Frontage.
Wetland areas planted with a SuDS Meadow Mix and Marginals.
Linear SuD Systems /Scrapes.
Foul Water Drainage
It is proposed that foul water that flows from the development will discharge via gravity to the public sewer, reusing the existing connection.
Surface water disposal will be managed via SuDS (sustainable drainage systems).
Control measures to prevent pollution will be provided as part of a robust treatment train.
Flood Risk
The site is located entirely within Flood Zone 1, which is the most suitable zone for all development types in terms of fluvial flood risk.
The site is also at very low risk from all other potential sources of flooding – tidal, reservoir, surface water, groundwater and sewer.
Sustainability
Our high sustainability standards ensure that the buildings we deliver stand the test of time.
Designed to achieve high sustainability and energy efficiency credentials (including BREEAM ‘Excellent’ and an EPC ‘A’ rating).
Water and energy efficient industrial/employment facilities that include the use of low and zero carbon technology like solar panels and air source heat pumps to reduce energy demand for future occupiers.
Buildings constructed using modern sustainable materials, including bio-based and recycled materials.
Secure cycle storage and routes to encourage alternative modes of transport.
Good levels of daylight/sunlight, air quality and acoustic performance.
Responsible sourcing of materials.
The management of waste sustainably and efficiently during construction.
Minimising surface water run-off and provision of SuDS.
Biodiversity enhancements.
Economic Benefits
Q&A
Shinfield Park, formerly known as Shire Hall, is a vacant office building and the wider site is underutilised, formerly being used for car parking. Over the past few years, the demand for large office spaces outside town centres, like Shinfield Park, has decreased as more businesses look for smaller and more central office locations instead. With this in mind, we are proposing to redevelop the site to provide modern, high quality and sustainable industrial/employment buildings. These facilities will bring the site back into active economic use, help to address the local demand for industrial/employment floorspace and provide new employment opportunities for local people, both during construction and when operational.
The existing Public Right of Way that runs from Railton Close through the connecting to Greenwich Road will be retained and will be accessible throughout the construction period.
The tallest building will have a maximum height of 12m (16.57m to ridge). This is significantly less than the current office building on the site. Our landscape strategy includes substantial boundary planting that will provide screening for the new buildings and will minimise any potential visual impact on neighbouring residential areas.
Yes, the site will be operational 24/7. While offices tend to have a high volume of traffic that peaks during the morning and evening rush hours, industrial/employment facilities tend to have lower volumes of traffic that are spread out throughout the day and night.
Previously, there was a limited bus service to the site, provided by the 603 Park and Ride route. However, following the previous occupier vacating the site, the bus operator decided to amend this route, so the 603-bus route no longer serves the site.
A Tree Survey has been undertaken so that we know the location and quality of each tree on the site. We will be retaining as many trees as possible. A detailed landscape and planting strategy will be developed to include new trees and native shrubs, wildflowers and meadow planting.
If planning permission is granted in late summer/late autumn 2025, we would expect construction to start towards the end of 2025. Based on our experience with similar schemes, we expect that construction could take around 18-24 months. These dates are indicative only and subject to change as the design and planning process progresses.
A framework Construction Environmental Management Plan (CEMP) would form part of any future planning application and would be a condition to planning permission. This would require the development to comply with agreed standards and methodologies for construction logistics, access for construction vehicles, dust mitigation measures, pollution control, disturbance minimisation and any other construction matter deemed relevant for the site. The final CEMP would be the result of extensive discussions with Wokingham Borough Council. Any appointed contractors would be required to provide updates to local residents on the nature of works to be conducted and the dates for those works. A site manager would be appointed to act as the primary point of contact for construction-related enquiries.
The scheme would be designed to achieve sustainability and energy efficiency certifications including BREEAM ‘Excellent’ and an EPC ‘A’ rating (the highest energy efficiency rating for buildings in the UK). The buildings could include water and energy efficient features such as solar panels and air source heat pumps to reduce the energy demand for future occupiers. We are also actively exploring the use of modern and sustainable construction materials that could include bio-based and recycled materials.
The Site is an established employment site and within the adopted Wokingham Local Plan there is a general presumption against the loss of employment land to non-employment uses. We are looking to bring forward a scheme in line with local planning policy, which retains the site in meaningful employment use and offers a range of quality, modern employment buildings aimed at appealing to a wide range of end users across all employment uses (excluding offices other than ancillary provision) including manufacturing, assembly and R&D.
The proposed development will generate fewer peak hour trips than would have been generated by the previous occupier and could be generated by another occupier using the existing buildings for office use. The nature of the proposed units is such that it will attract a wide range of occupiers across all employment uses apart from office use, many of whom will operate longer hours than a typical office use or 24/7 meaning that there will be a number of different shift patterns across the day, none of which start or finish during peak periods. As a result of this, the number of trips on the surrounding highway will be lower during peak periods compared to the previous or potential future office use of the site. On this basis, there is no requirement to make improvements to any surrounding junctions. This approach to the trip generation for the existing and proposed uses on the site has been agreed with WBC highways as part of the pre-application process. This is also reflected in the reduction in car parking provision from over 1,000 spaces currently to in the region of 250 spaces for the proposed development (final layout yet to be finalised).
As above, there will be a net reduction in trips associated with the site in peak hours compared to what the site previously and still could generate as an office development; therefore, no mitigation will be required for this junction. All major developments in the area which will have had an impact on the M4 J1 will have considered whether any improvements are required, and National Highways would have insisted on these being provided if considered necessary. The difficulty with major motorway interchanges is that there is little scope to make improvements without multi-million-pound projects which would not pass the planning obligation tests for the majority of planning applications.
At this stage (15th January 2025) we are seeking the views and feedback from the community, once the consultation period has finished, we will then take the feedback onboard and finalise our proposals before submitting our Planning Application in early Spring to Wokingham Borough Council.
Yes we have done a complete survey on all the trees within the site area. Our approach is to retain as many of the quality trees identified as possible. Our Planning Application will be accompanied by a detailed Aborcultural Impact Assessment which provides the details of the surveys we have undertaken and what we are proposing to remove. Our Landscape proposals will provide details of planting in lieu of any losses of trees.
We have used the trip rates that the former office site generated and compared it to what is proposed. If the site was re-occupied for office use it would generate a higher number of trips compared to the proposed development for Industrial/employment use, which will see a reduction of the number of trips, particularly at peak times, on the site. Varying shift patterns with also contribute to reducing trips during the peak rush hour periods. Full details will be supplied in the Transport Assessment that will accompany the Planning Application.
We are aware there is some asbestos, but to give everyone some assurance, our contractors will have to comply with all the legislation and safety requirements of the Health and Safety Executive. Before any demolition works start an Asbestos Survey will need to be undertaken to identify where the asbestos is and how much of it is onsite. The removal of any asbestos will be managed and removed in full compliance with the Health and Safety Executive.
Unit 1 has a maximum haunch height of 12m but at its ridge its 16.5m (middle of the building at the top of the roof). The existing building at its highest point is 29m, so our building will be substantially lower than the existing building on the site.
All trees that are being proposed are in line with best practice in terms of how they are planted to ensure their best survival. However, Woking Borough Council would expect that if any new trees that are planted die within 5 years they have to be replaced.
Yes we are proposing a typical chunky post and rail timber fence - we want to encourage and provide easy access for hedgehogs and other wildlife.
For a development such as this when we are applying for different uses, it is always a bit of a balancing act as there are no particular occupiers in mind, at this stage. The amount of parking currently proposed is in accordance with Wokingham Borough Councils parking standards and we have discussed the level of parking provision with the Highway Officer who is comfortable with the proposed provision at this stage. The 226 proposed parking spaces will be allocated to the units and there is an additional overflow car park to the north of the site, should any occupiers require additional parking spaces. Based on previous and similar size developments we have delivered and the parking standards, we are comfortable that this is an appropriate level of parking.
There are a couple of ponds to the south west of the existing building that we understand have been there for quite a long time and were created as part of the original development. There is also existing drainage that runs through the woodland to the south and we will not be touching any of that and they will continue to drain as existing. As part of our development we will be bringing forward a site wide Drainage Strategy that will ensure the existing ponds do not overflow with any excess water that the new development could create. We have had some Ecology Surveys undertaken and the intention is for minimal intervention so as to protect the existing ecology. We are however looking to make some enhancements directly to the north of the ponds to create some nice amenity spaces for employees and visitors using the site.
This will depend on the businesses that move into the site as different levels of industrial users will have different levels of employees. At the upper end we have estimated about 560 employees. However, it is important to note that it is unlikely that all the employees will be working on the site at the same time given the nature of the uses, as there are likely to be shift patterns throughout a 24 hour period.
This is not something we have looked into in any detail at this stage, but it could be considered if required.
At this stage we do not have any confirmed end users who could occupy the units in the future. Therefore, it is really important that we secure flexibility for a wide range of uses across the full extent of employment uses which cover pure industrial, manufacturing assembly and R&D. The employment use we would not be applying for is offices (excluding that which would be ancillary to another employment use).
A typical home is about 8m to the ridge, and the nearest unit to the residential area to the north is Unit 5 which is 10m to the haunch. However, the distance between the northern elevation of Unit 5 and the nearest residential property is 41m and there are also level changes and existing and proposed landscaping which will mitigate views.
If our planning application is approved by Wokingham Borough Council we envisage the development of the site will take approximately 18 months to complete.
We have had some discussions around the use of the car park. However, at this point in time due to some internal works being carried out, the removal of the temporary office building and due to Health and Safety, it has not been possible for anyone to access the site. However, we are keen to help facilitate conservations and will encourage future occupiers to engage and be as accommodating as possible.
It is anticipated that in the morning peak rush hour, based on our current proposal, there will be approximately 130 two way vehicle movements of which 5 would be lorries. Typically throughout the day there will be about 10/12 two way lorry movements per hour ( 6 in/6out at the worst case) throughout the day. The size of the units do not lend themselves for a large parcel distributer e.g. Amazon, that generate a large amount of lorry movements and therefore it is more likely to be manufacturing that do not have lots of lorries coming in and out throughout the day and is more likely to be 2 or 3 a day.
We will be applying for 24 hour operation, but the way the scheme has been designed we have tried to keep the yards in areas where they are not close to residential boundaries, and the position of the units also helps to screen potential noise outbreaks. Whilst some of the units might operate 24 hours a day, that does not mean that lorries will be coming in and out 24 hours a day and will certainly be less frequent at night. We will be submitting a Delivery and Servicing Management Plan as part of the Planning Application, which will outline how deliveries will be managed in the yards. There will also be a Noise Assessment which will identify whether any additional mitigation may be required in order to protect the amenity of the surrounding residential areas. We are very alive to this and will make sure that proper provisions are incorporated within the design to make ensure that the potential for disturbances is minimised and amenity is protected.
Our landscape elements for the scheme have worked so hard on the green infrastructure network across the site. The green infrastructure along the Public Right of Way (PROW) itself plays an important role in terms of visual amenity and how the edges of the site interacts with the woodland, the residential edges and the frontage of the site which is something users and people living in the surrounding area will experience on a day to day basis.
When we purchased the site it includes an area to the south that is currently dense woodland, which is priority woodland habitat and is heavily protected by planning policy. There is no intention to build on this woodland and any application proposing the loss of woodland would be unlikely to gain planning approval as the ecological impact would be severe.
The maximum number of employees is based on a certain element of a 24 hour shift pattern on some of the units, so not all of the estimated 560 employees will be working on site at the same time. It is anticipated that some people will either cycle, walk, use the bus or car share. As part of the Planning Application we will submit a Travel Plan which will outline how the use of substantiable transport modes will be encouraged and will be supported by the provision of the facilities on the site including cycle parking and shower facilities.
The current Public Right of Way (PROW) on the site to the north is made ground and our aim is to widen it via changes to the boundary treatment but retain it as a made ground footpath.
There will be a Drainage Strategy submitted with the Planning Application that sets out how the site will be drained including foul drainage. We are not expecting a significant increase in foul drainage relative to the site's former use. If there have been problems in the past, then we will look into this, as it is in our interests to make sure the foul drainage is sufficient and is going to work.
We are looking to propose solar panels on the roofs of all the units and the potential for air source heat pumps. We are also looking at trying to reduce energy use through the design of the units, including in terms of insulation.
We are already considering security on the site. Once the site is operational there will be Managing Agents and an Estate Management Plan, which will be assessed and reviewed on a regular basis. It is in our interests, and that of our future tenants to ensure there is as little or no vandalism and anti-social behaviour on the site. The design of the buildings also gives lots of opportunities for passive surveillance, which should be a deterrent to vandalism and any anti-social behaviour.
We did discuss this with Reading Buses and they have decided to stop this route and as far as we understand there are no plans to bring this stop back.
The access is staying the same so any vehicles coming from the M4 J11 can continue to turn left into the site. All other movements are via the signalised junction.
The floor level to unit 1 will be lower than the existing ground floor level of the building by approximately 3.4m. For context, this is about 0.5m above the upper basement level. The existing car park where unit 5 is located is on quite a steep slope so level differences will vary. A majority of the unit will be higher than existing levels with the north end of the building lower than existing levels.
As part of the planning application we will be submitting a proposed Lighting Strategy for the site which will look to provide sufficient lighting to ensure safe operation, but in a way which respects the site’s sensitive surroundings, including in relation to ecology as well as residential amenity. Lighting will automatically dim to lower levels enough to cover health and safety services when there is no movement in the area. If there is movement on the roads/area by cars/pedestrians etc the applicable fixtures will automatically ramp up. No lighting will spill outside the boundary of the site.
The landscaped area to the very north will maintain existing levels. The buffer and screening will be created through planting.
The bunker, which has previously been stripped out prior to Wrenbridge purchasing the site, will be removed as part of the proposed demolition of the building.
Planting to the north of the site is proposed as significant tree planting to create a buffer between the residential edge and the industrially active centre of the site. Structural planting will be proposed to this area at semi-mature/extra heavy standard.
Any future occupiers will be obliged to operate in accordance with the planning permission which seeks a range of uses. At this stage the end users for the units are currently unknown.
The safe storage, handling and disposal of hazardous waste is controlled and managed under specific legislation which places a duty of care on those involved to adhere to strict regulations. As such we would not expect any planning permission to impose additional controls in this respect.
Timeline
Throughout the pre-application planning programme, we will be in ongoing discussions with planning officers and stakeholders about our emerging ideas to redevelop the site.
The timings set out below are target dates and are subject to change as we progress through the design and planning process.
Wednesday 15th January 2025Live Public Webinar with Q&A session and launch of consultation.
Wednesday 29th January 2025Deadline for comments. Consultation period closes at midnight.
Early 2025Submission of planning application to Wokingham Borough Council (WBC).
Late Summer/Early Autumn 2025
Expected determination of planning application by WBC.
End of 2025Works to start on site, subject to planning permission being granted.
If you want to chat to a member of the team, give us a call: 07467 482 284 (Monday to Friday, 9.30am to 5.00pm)
We take data protection seriously. Please only provide your personal details if you are willing for them to be used by Stantec and the project team for the purpose of research in connection with this project and in order to update you on the progress of the project. Your details will be treated as confidential and will not be shared, passed on or used by any third parties and they will only be retained until the end of the planning process for the project, after which time they will be deleted. If you wish to withdraw consent to the processing of your personal data you may do so by emailing: shinfieldpark@stantec.com
We take data protection seriously. Please only provide your personal details if you are willing for them to be used by Stantec and the project team for the purpose of research in connection with this project and in order to update you on the progress of the project. Your details will be treated as confidential and will not be shared, passed on or used by any third parties and they will only be retained until the end of the planning process for the project, after which time they will be deleted. If you wish to withdraw consent to the processing of your personal data you may do so by emailing: shinfieldpark@stantec.com
Notification
Earlier in the year we obtained permission from Wokingham Borough Council to demolish the existing buildings on the site. Since the site preparation and demolition works began in early July, we know they may have caused some disruption to daily life, and we sincerely apologise for any inconvenience and frustration this may have caused.
Please be assured that we are doing everything possible to minimise disruption and to carry out our work in a considerate manner that respects both the community and the environment.
We remain on schedule to complete all main structural demolition works by Friday 31st October 2025.